Plan-Actual Comparison

 Here you can find a comparison of plan values and work logged on the level of project, componenets and issues.


Accessing Plan/Actual Comparison

You can either access the plan/actual sheet via the JIRA project tab

or via the ictime navigation

When accessing the plan/actual comparison via the ictime navigation, you have to choose a project first when entering the plan/actual comparison.

Basic Structure of the Plan/Actual Comparison

The plan/actual comparison sheet consists of the filter bar, the project section and components.

Filter

The filter bar helps you to restrict the display to a project (only if called via ictime navigation) and component.

If you filter by component, the plan/actual comparison value on project level will not consider this filter. Reason is that plan values might be generic, and it does not make sense to compare a generic plan value that has been set for a whole project with real values that are filtered and do not include all components.

Plan/Actual Comparison for Project

This is the highest plan/actual comparison level.

FieldDescriptionRemarks
PlanPlan value on project level.either generic or as result of all plan values of all components
ActualWork (time) logged on all issues of the project. 
DifferencePlan minus time logged.due to JIRA options for handling of remaining estimate this value is not necessarily the same like the remaining estimates
QualityA quality factor for the overall project planning. The indicator is calculated based on the quality factor of all components.

The quality factor can only be calculated if there is at least one issue that

  • has an estimate
  • has time logged
  • and is resolved or closed.

Plan/Actual Comparison for Components

This is the second plan/actual comparison level. If you did not define components for your project in JIRA, ictime will automatically display a component "Without Component".

Field/OptionDescriptionRemarks
PlanPlan value for component.Can either be generic or retrieved form the issues of this component, see Planning Sheet and Planning Concept.
LoggedWork (time) logged for all issues belonging to this component. 
Remaining

The "remaining estimate" value from the respective JIRA field for all issues of that component.

Only displayed if the plan values for the component are calculated from issues of the component - not displayed if the component has been configured to use a generic estimate.

Keep in mind that this is not necessarily the difference between plan and logged, as JIRA offers various options how to set the remaining value when cerating/editing an issue and when logging work.
DifferenceThis is the real effective difference between planned and logged for all issues of that component. 
QualityQuality indicator for planning on the level of this component. The indicator is calculated based on the plan/actual difference of issues of that component that are resolved or closed, and we consider the plan value amount, so issue with high plan values have an higher impact on the quality factor compared to issues that have low time estimates.

The quality factor can only be calculated if you have at least one issue that

  • has an estimate
  • has time logged
  • and is resolved or closed.

When clicking on the component, you get access to all issues of the component and can see the plan/actual comparison on issue level (see next chapter).

Plan/Actual Comparison for Issues

When clicking on a component, you get access to all issues of that component and can plan time on these issues. Issues will only be loaded in this moment, and we will store in your session that you have opened this component. This setting will be kept, even if you navigate through JIRA or ictime.

This way, you can see the plan/actual values for all issues in one place.

Field/OptionDescriptionRemarks
TaskTask key (clickable, directs you to the issue screen), name 
TypeIssue type 
StatusIssue status. 
AssigneeAssignee of this issue 
EstimatePlan value ("work estimate") for this issue. 
Remaining EstimateThe remaining estimate.Uses the respective JIRA field.
DifferenceThis is the real effective difference between planned and logged. 
QualityQuality indicator for planning on the level of this component. On issue level, quality is simply time logged divided by time planned. Quality 1 means that plan and actual result are the same, so the planning was perfect. Quality factors > 1 mean that you have spent more time than planned, and < 1 that you have spent less time than planned.

The quality factor can only be calculated if there is at least one issue that

  • has an estimate
  • has time logged
  • and is resolved or closed.