From this view, you can either delete the work log, or try to "repair" it.
Info |
---|
|
...
Field | Description | Remarks |
---|---|---|
Delete work log. | ||
repair work log. |
Info |
---|
Usually, JIRA restrictions regarding issue status are applied when editing a work log, you can't modify work logs for closed issues. However, in reports, those restrictions are not applied, and this also applies in case of repairing work logs. |
Repair Screen
Correcting a work log requires that configurations regarding teams & price lists of old and new project are compatible, i.e. basically that
- the user who has created the work log is in a team with a valid price list for the date of the work log for both projects
- or both projects are configured not to use teams & price lists.
If this is not the case, configuration of the new project needs to be modified.
Correction Possible
If both project configurations are compatible, you can just correct the work log.
Correction Not Possible - Further Actions Required
If both project configurations are not compatible regarding teams & price lists, you can't correct the work log but first have to change the configuration of the new project. You will see a screen like this:
As the user is not assigned to any team of the project (with a valid price list), you can't correct the work log. You need to assign the user to a team in the new project and ensure that there is a valid price list. Once done this, you can try again and now will be able to correct the work log: