Please note that planning in ictime is always time-based. Even though you can assign a cost/price to you work for time you log, we do not offer financial budget planning at this stage, but just time-planning. |
Table of Contents |
---|
...
Planning Approach
When doing the planning and when showing time planning values, we distinguish two kinds of values:
...
Tip |
---|
Even though it might be difficult to understand in the beginning, it is very simple. It's basically all about the component time planning value. By setting a generic plan value on component level, you decide that this value should be used for calculating the results for the project (top-down approach, not very detailed). By not setting it, you decide that the calculated result for the component (= work estimates for all task/sub-tasks of the component) should be used for calculating the project time budget (bottom-up approach, detailed). |
...
Examples
Have a look at the following example:
...