  1. Work estimates on task/sub-task level (this functionality is provided by JIRA and ictime uses the data). JIRA allows for entering values on the level of sub-task and task, and if both levels have work estimates, they are all added; so ictime usesthe total value on task level (for reasons of simplicity, we are not explicitely showing the sub-task level).
  2. Planning/estimates on component and project level. This is extra functionality provided by ictime.

Apart from having two different places to enter time budget planning information, there is also a specific approach for being able to manage rough time budget plans and detailing planning at the same time. This is explained in detail in this chapter.

Info

Please note that planning in ictime is always time-based. Even though you can assign a cost/price to you work for time you log, we do not offer financial budget planning at this stage, but just time-planning.

...