Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

LevelGenericCalculatedRemarks
Task A1-015h We have made a work estimate of 5h.
Task A1-0210h We have made a work estimate of 10h.
Task A1-0310h We have added this task and have made a work estimate of 10h.
Component A1 = 25hWe have deleted the generic value for component A1, as we have decided that the detailed planning for tasks of this component is ready now. So we only have a calculated plan value for this component of 25h from task level (doing the detailed plan on task level, we also realised that 30h was to much).
Task A2-0110h  
Task A2-0225h  
Component A2  =35hWe have deleted the generic value for component A2, as we have decided that the detailed planning for tasks of this component is ready now. So we only have a calculated plan value for this component of 25h from task level (doing the detailed plan on task level, we also realised that 20h was not enough).
Component A310h We have planned 10h for component A3. No work estimates for tasks yet, so still no calculated value.
Projekt A = 70hWe have deleted the generic value on project level, as we think that planning for components is now okay and reflects the overall time budget we will need. So we have a calculated value of 70h from component level, and big parts of that planning value is a result of work estimates on task level.
Tip

The example above shows a more detailed planning. Except for the component A3, where we do not have tasks with work estimates yet, we have decided to basically rely on the work estimates from task level, and we also have decided that planning is good enough to eliminate the general time budget for the project itself, as the data we get from lower levels is complete enough.

Info

If you don't use components and/or if you have tasks without component assignment, such tasks will be automatically summed up into a "virtual" component provided by ictime in order not to break the logic that all calculated values always need to come from the next-lower level("No Component"). You can't set a generic plan value for this "component" of course, but the calculated value will be considered for the project like it were a real component. This way, work estimates on task level are made available to calculate the planning value for the project without having a real component.

...