Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

As a conclusion and to cover both needs, you need to set top-down time budgets on a certain level, and at the same time, you want to use bottom-up time budgets that are derived from a more detailed planning on lower levels. How this can be reached is described in the following paragraph.

Time Planning Method

We distinguish a top-down time budget and a bottom-up time budget.

...

When doing the planning and when showing plan values, we distinguish two kinds of values:

Planning ValuesDescriptionRemarks
genericplan-values directly entered on this level, you set this valuepossible for components and project; on task level, this is simply the JIRA work estimate
calculatedtime is retrieved from lower levels, you see this value, but can't set itthis is a value calculated by ictime from available data on the next-lower level according to the logic explained below

Depending on the level (project, component, task) you are working on, these values have a slightly different idea:

LevelValueDescription
Sub-TaskgenericJIRA work estimate on sub-task level
 calculatedn.a.
TaskgenericJIRA work estimate on task level
 calculatedn.a.*
Componentgeneric 
 calculated 
Projectgeneric 
 calculated 

...

Expand
title* Note ... click here to expand

In fact, JIRA calculates the work estimate for a task as sum of work estimates of all sub-tasks + the work estimate for the task itself; but from ictime planning point of view, this is not a calculated value, as in our project time planning sheet, we do not show the sub-task level, but our starting point is the JIRA work estimate result on task level.

 

 

 

Have a look at the following example:

...